|
SIMULATION 1
CLIENT:
A
pharmaceutical manufacturer and distributor had outgrown their
old facility and was currently in the process of designing
a new state-of-the-art, paperless distribution center.
DESCRIPTION
OF OPERATION:
The
company manufactures small vision products that come in two
pack sizes. Most of the orders are picked using automated
order picking devices called A-Frames. Orders for items with
medium movement are batch picked from horizontal carousels
with computer controls and pick-to-light displays. The completed
orders are then routed towards, semi-automated packing stations
where they are arranged according to magnification, packed
into shipping boxes, and then conveyed to the respective carriers.
OBJECTIVES:
Before
investing an exhorbitant amount of capital, management wanted
to know if this proposed picking system would work. Gross
& Associates was retained to evaluate whether the conveyor
system would be able to support the projected high volume
throughput. In addition, the client wanted to test alternative
picking strategies and to determine the best combination of
picking systems. They also wanted to know the number of picking
totes to feed into the system to ensure constant work flow
without creating bottlenecks.
METHODOLOGY:
Gross
& Associates suggested a computer simulation study of
the proposed conveyor system. A simulation model was created
to follow the structure of the actual operation. Statistical
distributions of actual data were used as input into the model.
Statistical outputs at the end of the simulation runs provided
insight into the performance of the system. Animations of
the simulation runs revealed the location of system bottlenecks.
RECOMMENDATIONS:
Gross
& Associates recommended the following based on the simulation:
-
Eliminate the horizontal carousel picking system and distribute
more orders among the A-Frames. The use of carousels slowed
down the system to the point that it could not process the
required number of orders for the day.
-
Recirculate 800 to 1,000 totes. More totes led to increased
conveyor congestion, while fewer totes increased the time
required to complete a day's worth of orders.
-
Divert completed ordes to the closest open packing station
and maintain a working queue of at least one tote per packer
to keep congestion in the packing loop minimal.
-
Eliminate an on-line feed station for the shipping boxes
because it delays the order's movement down the system.
-
Install either high-speed conveyors or multiple conveyors
at a lower speed to transport totes to the five A-Frames.
RESULTS:
Without
simulation, the company would have installed millions of dollars
of sophisticated equipment, only to realize that the system
would not be able to perform at the desired level. With simulation,
however, necessary equipment modifications were identified
before any physical implementation. In addition, management
was assured that the system would be able to deliver the projected
order throughput. The capital for the project was approved
and the building is now under construction.

|